泄水洞爆破对邻近既有隧道衬砌结构的振动影响研究
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TU476.4

基金项目:

国家自然科学基金资助项目(52308272)


Study on the Vibration Effects of Drainage Tunnel Blasting on Adjacent Existing Tunnel Lining Structure
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为探究泄水洞爆破对邻近既有隧道衬砌结构的振动影响,以浩吉铁路北山二号隧道泄水洞工程为依托,采用现场监测和数值模拟方法,分析了泄水洞爆破作用下隧道衬砌峰值振速和应力变化规律。研究表明:原爆破方案下,绝大部分衬砌峰值振速严重超出安全允许振速(5 cm/s),且最大拉应力已高于衬砌混凝土极限抗拉强度,导致衬砌表面出现裂缝;泄水洞爆破对隧道迎振侧边墙影响最大,最大峰值振速达17.98 cm/s,超出安全允许振速。基于现场监测数据拟合所得的萨道夫斯基公式反算出最大单段装药量,提出了泄水洞优化爆破方案。数值模拟及现场监测表明,优化爆破方案的峰值振速均未超出安全允许振速。

    Abstract:

    To investigate the vibration effect of the drainage tunnel blasting on the lining structure of the adjacent existing tunnel, the drainage tunnel construction of Beishan No.2 Tunnel in Hao-Ji Railway was considered as the research background. Field monitoring and of dynamic finite element methods were used to analyze the variation laws of peak vibration velocity and stress of the exiting tunnel lining due to the drainage tunnel blasting. The results showed that under the existing blasting scheme, both on-site monitoring and numerical simulation indicated that almost all the peak vibration velocities of tunnel lining were much greater than the allowed vibration velocity of 5 cm/s. The maximum tensile stress was larger than the ultimate tensile strength of the lining concrete, resulting in cracks in the lining; and the blasting of the drainage tunnel has the greatest impact on the side wall of the tunnel facing the vibration source, with a maximum peak vibration velocity of 17.98 cm/s, significantly exceeding the allowed vibration velocity. Based on the Sadovsky's formula fitted from field monitoring data, the maximum charge amount per delay was calculated, and an optimized blasting scheme for the drainage tunnel was proposed. Numerical simulations and on-site monitoring confirmed that the peak vibration velocity of the optimized blasting scheme did not exceed the allowed vibration velocity, thereby ensuring the safety of the tunnel's main lining structure.

    参考文献
    相似文献
    引证文献
引用本文

郎军星,赵晓佳,高智,孙星亮.泄水洞爆破对邻近既有隧道衬砌结构的振动影响研究[J].河北工程大学自然版,2025,42(6):56-64

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2024-02-28
  • 修改日期:2024-04-18
  • 在线发布日期: 2026-01-08
  • 出版日期: 2025-12-25
文章二维码

《河北工程大学学报(自然科学版)》编辑部严正声明

关闭